28.2 MW
The first hydro phase forms the foundation of Betmai’s renewable-energy development, using a run-of-river weir arrangement.

The Betmai project brings together hydropower, complementary solar development and transmission infrastructure for Sierra Leone.

Bringing people and expertise together to advance renewable-energy development.
SERL is developing the Betmai Hydroelectric Project with a first hydro phase of 28.2 MW and an estimated first-phase cost of US$110 million.
The hydropower arrangement is a run-of-river weir. Complementary solar development is planned alongside the wider energy programme, with hydro and solar designed to evacuate power through a shared power substation into the Transco-CLSG network.
Meet the company behind BetmaiThe first hydro phase forms the foundation of Betmai’s renewable-energy development, using a run-of-river weir arrangement.
Solar development complements the hydropower programme. The two resources are designed to share a power substation.
A planned transmission line connects the Betmai powerhouse to the shared step-up substation, with power evacuated into the Transco-CLSG network.
The planned 12 km, 66 kV transmission connection links the Betmai powerhouse to the shared hydro–solar step-up substation. Both resources evacuate power through this substation into the Transco-CLSG network.
Explore the river and its surroundings.
River systems, biodiversity and local livelihoods shape the way renewable energy is developed. Environmental work and community participation sit alongside engineering and investment in SERL’s approach.